Tuesday, December 16, 2008

Minor Update

Kir went to check out the site as we have recieved the second invoice from PD which means our frame is totally complete!! Woo hoo!! But there has been more progress...


They've started the plumbing and electricals and put up the guttering as well as the safety rails for the roof tilers, which definately means roof tiles by Christmas!! I'm hoping they can finish it in a week and a half.




Our plumbing? Or is that electricals.. LoL

Our bi-fold frame.